MCQ on Construction Planning, Scheduling & Control

Objective Questions on Construction Planning, Scheduling & Control

If you are preparing MPSC, RSMSSB, TNPSC, Karnataka PSC, KPSC, APSC, TSPC, WBPSC, Vyapam, CGPSC, UPSSSC, UKSSSC, OSSC, HPSSC, DSSSB, JKSSB, BPSC, JPSC, GPSC Junior Engineer or Assistant Engineer Civil exam and searching the topic wise objective type questions for preparation of the said exam, then your are in right place. here we are providing the study material/Sample paper/ model paper for the above said exam.

In the execution of a project, the main objective of planning is
(a) Completion of project most economically and well in time
(b) Completion of project safely and economically
(c) Completion of project only economically
(d) Completion of project only in time

The planning is to be done
(a) By the contractor only
(b) By the owner only
(c) By the architect only
(d) By the owner and contractor both

The functions of the construction management are
(a) Planning
(b) Organising
(c) Direction and controlling
(d) All the above

Management is necessary for
(a) To effect economy in the cost of construction
(b) To improve quality and speed of work
(c) To check wastage of material and labour
(d) All the above

Scheduling help in
(a) Planning for the project
(b) Financial control of the project
(c) For preparing estimate of the project
(d) Completing the project in an orderly and effective manner

A milestone chart is
(a) Inferior than the bar chart
(b) Same as the bar chart
(c) An improvement over the bar chart
(d) None of the above

PERT technique can be used for
(a) Research and Development Projects
(b) Repetitive type projects of small housing construction project
(c) Research, development and repetitive type projects
(d) None of the above

Zero slack indicates that the project is
(a) On schedule
(b) Behind the schedule
(c) Ahead of the schedule
(d) All the above

CPM network is
(a) Event oriented
(b) Acitivity oriented
(c) Both event as well as activity oriented
(d) Neither event nor activity oriented

In a network, critical path is
(a) Always the longest path
(b) Always the shortet path
(c) Middle path
(d) None of the above

The time corresponding to minimum total project cost is called
(a) Optimum time
(b) Crash time
(c) Normal time
(d) Optimistic time

During the stages of construction work, the process of controlling the expenditure is known as
(a) Time control
(b) Quality control
(c) Cost control
(d) None of the above


Posted

in

by

Tags:

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *