Bihar SBTE Diploma Civil 5th SEM Dec 2019 Paper on Estimation & Costing
Sr. No. | Questions with options |
1 | What are the main points to be considered while preparing detail estimate
(a) Availability of materials (b) Quality of materials (c) Carriage facilities (d) All of the above |
2 | In wooden works, the measurements of chaukhat is in cubic meter, then the measurement of shutter is in
(a) Square meter (b) Meter (c) Cubic meter (d) None of these |
3 | The payment rate of AC sheet roofs is done in _____
(a) Per unit length (b) Square meter (c) Cubic meter (d) Per 1000 kg |
4 | The thickness of layer while filling a pit with earth should be generally ______
(a) 10 to 20 cm (b) 20 to 50 cm (c) 50 to 75 cm (d) 80 to 100 cm |
5 | As per I.S 1200 the correct measurement should be taken up to
(a) 0.01 m (b) 0.01 cm (c) 0.01 mm (d) 0.1mm |
6 | In rate analysis, the contractor’s profit should be considered as _____
(a) 10% (b) 5% (c) 3% (d) 1.5% |
7 | The capacity of 8 ton truck for carrying number of bricks is _____
(a) 3000 (b) 2500 (c) 2000 (d) 1800 |
8 | Generally one bag of cement in India weight
(a) 30 kg (b) 50 kg (c) 40 kg (d) 60 kg |
9 | The cover for steel bars in R.C.C beam is
(a) 25 mm (b) Twice the diameter of the main bar (c) Which ever is greater in ‘a’ and ‘b’ (d) None of these |
10 | The additional length of one hook in the steel reinforcement to bars is _____(where d = diameter of bar)
(a) 4.5 d (b) 9 d (c) 12 d (d) 18 d |
11 | The expected out turn of cement concrete (1 : 2: 4) per mason per day is
(a) 2.0 cubic meter (b) 2.5 cubic meter (c) 3.5 cubic meter (d) 5.0 cubic meter |
12 | The carpet area of the building excludes the following
(a) Verandah (b) Store (c) Garage (d) All of the above |
13 | The volume of cement required to prepare 10 cubic meter of 1 : 2: 4 concrete is
(a) 2.o cubic meter (b) 2.3 cubic meter (c) 2.2 cubic meter (d) 2.4 cubic meter |
14 | Actual size of modular brick is
(a) 15 cm x 10 cm x 9 cm (b) 19 cm x 9 cm x 9 cm (c) 20 cm x 10 cm x 9 cm (d) None of these |
15 | The amount of lime required for one coating of white washing of 100 square meter plaster is
(a) 10 kg (b) 15 kg (c) 20 kg (d) 25 kg |
16 | The payment unit for the steel in grill work is in
(a) Volume (b) Weight (c) Both (a) & (b) (d) None of the above |
17 | The reinforcements bars should be tied with ________ SNG (binding wire) annealed with gauge of
(a) 20 (b) 16 (c) 25 (d) 12 |
18 | Provision for sanitary work in percentage on detailed estimated cost is
(a) 35% (b) 25% (c) 15% (d) 10% |
19 | The approximate cost of the complete labour as percentage of total cost of building is ______
(a) 5% (b) 10% (c) 25% (d) 40% |
20 | Provision of contingency in small project work is ______
(a) 10% (b) 8% (c) 5% (d) 3% |